According to the original plan, the last remaining Russian plutonium production reactor, ADE-2, was scheduled to shut down in 2010. However, NNSA believes that the reactor could be shut down earlier - in the fall of 2009.
Zheleznogorsk reactor shutdown schedule
4 TrackBacks
TrackBack URL: http://www.fissilematerials.org/cgi-bin/mt/mt-tb.cgi/387
The last Russia's plutonium production reactor, ADE-2 in Zheleznogorsk, will indeed be shut down earlier than it was originally planned (in 2010). Construction of the replacement heat-generating plant in Zheleznogorsk is expected to be completed in the... Read More
The date for the shutdown of the last Russian Pu production reactor, ADE-2 in Zheleznogorsk, is set to May 31, 2009. It is not clear, however, if the power plant that is supposed to replace ADE-2 in providing heat for... Read More
Russia's last plutonium production reactor, ADE-2 at Zheleznogorsk, was shut down at midnight on May 31, 2009 (at 24:00 MSK according to one report, which was 04:00, June 1st in Zheleznogorsk). The shutdown is not permanent yet - officially, the... Read More
Russia's last plutonium production reactor, ADE-2 at Zheleznogorsk, was shut down at midnight on May 31, 2009 (at 24:00 MSK according to one report, which was 04:00, June 1st in Zheleznogorsk). The shutdown is not permanent yet - officially, the... Read More