Construction of spent fuel storage facility in Zheleznogorsk to resume

| 0 Comments | 2 TrackBacks

In April 2008, Spetsstroy, the company that was building the spent fuel storage facility in Zheleznogorsk, suspended the construction citing financial dispute with Rosatom. Rosatom responded by launching a tender for the completion of the project. This week, the contract was awarded to the "Gruppa E4" (Group E4) company.

Group E4 will build dry storage for spent fuel of RBMK-1000 and VVER reactors at the cost of 9.5 billion rubles (about $390 million). It will also upgrade the existing pool storage facility that contains VVER-1000 reactor fuel. The cost of this project is 420.5 million rubles (about $17 million).

2 TrackBacks

TrackBack URL: http://fissilematerials.org/cgi-bin/mt/mt-tb.cgi/1523

Rosatom plans for Zheleznogorsk from Nuclear power and proliferation on September 9, 2008 5:20 AM

During his visit to Zheleznogorsk, Sergey Kiriyenko, the head of Rosatom, announced the plans to build a large spent fuel storage and reprocessing hub in Zheleznogorsk. The first part of the plan includes completion of the spent fuel storage facilities... Read More

Russia commissioned the first stage of the centralized dry storage facility at the Mining and Chemical Combine in Zheleznogorsk. When completed, the facility will be able to receive spent fuel of two types of reactors - RBMK and VVER-1000.The capa... Read More